GREENHYDRO successfully completed the repair and reinforcement works of a 19 km DN1000 mm GRP (FRP) pipeline within the Fast Track Water Treatment Plant Project in Iraq. During the project, 1,900 Lamination applications were performed, eliminating severe water leakages and joint weaknesses on the line. All sections passed comprehensive hydrostatic tests and the system was safely commissioned. As a result of this rehabilitation, the line now provides efficient and reliable water transmission, contributing to the sustainability of the region’s critical infrastructure.
With our technical know-how, experience and expert team, we continue to be a reliable solution partner for our project stakeholders in Türkiye and abroad. We closely follow industry developments and implement them in our field operations to deliver cost-effective, long-lasting and functional solutions.